Developer: Energie Wasser Bern
Client: BSH Umweltservice, Sursee
Place: Bern
Project: washed fly ash conveyor, conveyor for bottom ash discharge
Year of construction: 2012
Environmentally friendly energy generation from domestic and industrial waste for district heating and electricity is an important task of Energie Wasser Bern. All waste from the Bern region is processed in the new waste incineration plant. This corresponds to around 110,000 tonnes of waste per year.
Developer: Energie Wasser Bern
Client: BSH Umweltservice, Sursee
Place: Bern
Project: washed fly ash conveyor, conveyor for bottom ash discharge
Year of construction: 2012
Project
As subcontractor, Frei Fördertechnik AG took on the planning, manufacture as well as the installation and commissioning of the ash loading system of KVA (waste-to-energy plant) Bern. In both projects, one important criterion was to load the truck troughs as well as possible in order to optimise the transports. The goal was achieved with the use of shuttles and reversing belts with different discharge positions.
Special features
Technical data
Feed material: washed fly ash, bottom ash
Feed capacity: max. 3.5 t / h
Feed sizes: 0 – 100 mm
Installed components: 3 conveyor belts in total, electromechanical drive and shifting devices