12. April 2023
The old gravel works was partially dismantled. The old conveyor belts and screening machines were lifted out of the building.

Maximised productivity
The old gravel plant was partially dismantled. The old conveyor belts and screening machines were removed from the building.
A new steel structure was erected and the new machines, such as a new impact crusher, conveyor technology and dust extraction system, were installed and commissioned.
Following this conversion of the plant, productivity will be maximised, environmental efficiency increased and the plant will comply with the latest safety and operating standards.
We would like to thank Carrière de Sous-Vent for this fantastic order and the excellent team from Monthey for the perfect implementation of the project – well done!