Kieswerk Oldis AG, Haldenstein in operation - It's up and running!

14.09.2022 - It's up and running! The new gravel plant of Kieswerk Oldis AG in Haldenstein has been in operation since the end of June 2022. To date, over 40,000 t of raw material have already been processed. Thanks to all involved for the extraordinary cooperation!

14.04.2022 - The storage conveyor is flying high. The construction of the system is proceeding at a rapid pace. Today, the belt conveyor and the distribution conveyor have been installed.

18.02.2022 - The snow is about to melt away under our skis: the thermometer climbs to 18 degrees today! The best conditions for the commissioning of the gravel plant for Kieswerk Oldis AG.

27.01.2022 - The construction is finished, the treatment plant and the purification technology are in the starting blocks. As soon as the temperatures are no longer so icy, we will start commissioning.

Mit dem neuen Werk wird es möglich, Restbaustoffe, Recycling und Aushubmaterialien neu aufzubereiten und als hochwertige Baustoffe wieder in den Materialkreislauf zurückzuführen.

Damit investiert das Unternehmen weiterhin in sein innovatives Angebot und leistet einen Beitrag an einen nachhaltigen Umgang mit Ressourcen und macht einen weiteren Schritt in eine erfolgreiche und umweltfreundliche Kreislaufwirtschaft.


Project information

Non-metallic minerals

Kieswerk Oldis AG